Proposed Blasting Works

Roadbridge wish to advise of the upcoming drilling and blasting operations scheduled to commence in mid June 2019. The dates are provisional and depend upon site conditions and project schedule. Exact dates and times will be posted locally in advance of the blasting operations taking place.

Roadbridge shall endeavour to post updates on the N4 Project Website when the dates are confirmed.

Please see our Works Schedule for exact time and locations

Proposed Date Location Comment
June 2019 Carrownagark, Riverstown One Blast per week

You can also follow the progress of the project by downloading or reading online our quarterly newsletter.

You can also get an update of the project by following our Gallery which will be updated as work progresses.